Project Overview

Location: Sault Ste. Marie, ON
Client: Brookfield Renewable
Services: Geotechnical & Dam Engineering, Materials Testing, Construction Management
Sector: Energy
Completed: 2022

Project Description

TULLOCH completed dam-raise design and construction QA/QC for the Aubrey Falls Control Dam and Trolling Lake Block Dam, part of Brookfield Renewable's MPT Evolugen system. The IFC design package and construction were completed between 2021 and 2022.

The assignment extended from design and permitting through construction verification, materials testing, field QA/QC, as-built documentation, and completion reporting.

Scope of Services

  • Dam-raise IFC design package and specifications
  • Supporting permits and approvals
  • Construction-material verification
  • Field QA/QC during construction
  • Materials testing and inspection
  • As-built drawings
  • Dam-raise construction completion reports