TULLOCH prepared a stormwater management design brief to accompany the proposed expansion of an industrial site building.

The site plan and stormwater management design included a review of the site’s access design and the fire route servicing the facility from the municipal roadway. We designed a site plan, stormwater management, grading for the facility expansion, and site servicing to connect the building to municipal infrastructure for water, sewage and drainage. 

Civil Design Engineering

The design added approximately 4,000 m2 of building area and 6,000 m2 of work yard laydown area. The site has frontage on Highway 11, so we had to meet MTO requirements for corridor setbacks and drainage. The result—a 500 m2 stormwater facility—complied with MTO and Municipal requirements